Long Lots Elementary School
The Long Lots School Building Committee is seeking approval of $6.8 million to design a new elementary school to replace the 70-year-old building on Hyde Lane.

By John Schwing

WESTPORT —  The Long Lots School Building Committee is formally asking for $6.8 million to begin designing a new structure to replace the seven-decade-old elementary school — a project estimated to cost nearly $100 million when complete.

The committee convened a brief online “special” session Friday afternoon, on advice of the Town Attorney’s Office, to publicly act on its funding request prior to presenting it to the Board of Finance meeting Wednesday, Feb. 7. That meeting will take place at 7:30 p.m. in Town Hall’s auditorium.

The $6.8 million request, in fact, was included on the finance board’s agenda, per a Wednesday revision, even before the LLSBC on Thursday posted a public notice of its Friday meeting to request approval for the money.

The last-minute Friday meeting was described as “a housekeeping” matter by Jay Keenan, the building committee chairman and RTM District 2 member — scheduled at the recommendation of Town Attorney Ira Bloom.

The $6.8 million, several committee members noted, is part of overall projected expenditures to build a new Long Lots Elementary School. The total amount, according to a document the committee has submitted to the Board of Finance, is estimated to be $98.2 million.

The request for design fees was approved Friday by a unanimous vote of LLSBC members, forwarding the proposal to the finance board next week.

The $6.8 million in design fees, if approved by the Board of Finance and Representative Town Meeting, will increase the town’s debt service by $467,000 for 20 years beginning in 2025, according to the document filed with finance officials.

A capital expenditure to actually construct the new school — estimated at $85 million, with anticipated 15-16 percent reimbursement from the state — would be formalized based on recommendations by the architect and engineers hired to design the project.

If the design fees are not approved, “the project cannot go forward,” the document states.

With approval of design fees, the largest share — $6.2 million — would be spent to hire an architect, mechanical, civil/site and structural engineers, and peer review consultants, although specific amounts for each of those professional services were not detailed Friday. The rest would be allocated: $190,000 for a construction manager/pre-construction services, $175,000 for a town manager/representative, $195,000 for site tests, studies and borings, and $40,000 for printing and miscellaneous costs.

Requests for competitive bidding on the design jobs, however, have yet to be issued by the committee.


“We tried to do this in executive session, [but] the temperature did not warrant going into executive session … I would have preferred, and I think I’m not alone, to not showing this [budget] number, but that was not an opinion that won the day.”


Don O’Day, Long Lots School Building Committee member

That prompted Richard Lowenstein, a District 5 RTM member, to ask why the committee had disclosed its budget for design consultants prior to seeking bids.

Describing his own question as “naive,” Lowenstein asked: “Why do you tell people who are going to bid on the project how much you are willing to pay as opposed to what they offer?”

“This is very confusing,” he said, adding it gives professionals bidding on the design team jobs “no incentive” to bid lower.

Don O’Day, a building committee member and District 3 RTM member, agreed with Lowenstein, saying the question was not “naive.” He said he also finds it “totally, completely, 100 percent inappropriate” to publicly disclose the design budget before seeking competitive bids.

But, O’Day added, “We tried to do this in executive session, [but] the temperature did not warrant going into executive session — it is what it is. 

“I would have preferred, and I think I’m not alone, to not showing this [budget] number, but that was not an opinion that won the day,” he added.

Asked by Lowenstein who made that decision, O’Day confirmed it was the Town Attorney’s Office.

Another question was raised by Toni Simonetti, who asked whether the design team would be allowed to consider options for the project other than the 8-24 application approved last month by the Planning and Zoning Commission.

Specifically, she wondered if designers could be given leeway to consider excluding use of “terrace 1” on the Long Lots property, the current site of the Westport Community Gardens.

The answer is “no,” Keenan told Simonetti. “We have an approved 8-24 from Planning and Zoning, and that is what we are proceeding with.” That plan includes using the garden site for a multi-purpose athletic field and relocating the gardens.

John Schwing, the Westport Journal consulting editor, has held senior editorial and writing posts at southwestern Connecticut media outlets for four decades. Learn more about us here.