A rendering of the proposed Long Lots School - Photo Svigals + Partners, Depiction, LLC
A rendering of the proposed Long Lots School – Photo Svigals + Partners, Depiction, LLC

Editor’s note: Following is an opinion submitted by Jennifer Johnson, an RTM member from District 9.

The majority of Westport residents strongly support replacing the existing Long Lots School, with good reason.  The proposed building is truly spectacular, and the Long Lots Building Committee (LLBC), a volunteer group, deserves our thanks for its hard work and vision. 

The elephant in the room, however, has always been the enormous cost, which is now approaching $110 million and likely to go higher.   Were more cost-effective alternatives adequately contemplated? Will there be enough money left over to cover other pressing capital projects like renovations to Coleytown Elementary or a new Fire and Police HQ?   Can the average Westporter really afford to pay 4% more in taxes for just one school when so many other large projects are coming down the road?

The public never had a real chance to have that dialogue because RTM leadership pushed the final Long Lots approvals through at record speed with minimal input or transparency.  Why?  Leaders claimed they made a mistake in calendaring a state grant deadline; in order to avoid additional interest expenses, they argued, the final project approvals had to be rammed through by mid-June.  

The result scrambled the normal review process, impeding the public from having a robust debate around the costs or tax consequences before the looming self-imposed deadline.  For that reason it is not surprising that a member of the electorate has now decided to launch a petition for a referendum on the issue, as provided for under our Town Charter, asking to cap the expenditure at $90 million. 

Here are some of the facts and issues that led us to this place:

Jennifer Johnson, Member RTM, District 9
Jennifer Johnson, Member RTM, District 9
  • After years of LLBC meetings focused mostly on design specs and engineering, five different town boards and commissions were forced to fast track the required approvals in the space of about a week in June.  
  • In that short time, the appropriation request changed three times before the final $103,190,124 RTM vote on June 12th.  This amount is in addition to a prior $6.8 million design appropriation, bringing the total to $109,909,124.
  • If past experience is any guide, the current total is likely to rise with inflation and tariffs driving up the cost of construction.
  • Contrary to the way other prior town school construction projects were handled, and in violation of Connecticut’s Freedom of Information Law, RTM leadership insisted on reviewing the LLBC budget in executive (closed) session.  This deprived the public of its ability to meaningfully review and question costs in this massive disbursement. 
  • Because of the fast tracking process, roughly 1/3 of RTM members never even had the opportunity to  review a cost breakdown before they voted to approve the appropriation.
  • The expedited Long Lots review process ended up overlapping with a slew of public hearings by many of the same town bodies in connection with another massively complex and expensive project, the Hamlet in Saugatuck.  As a consequence of this poor planning, which could have been avoided, the last minute crisis mode was intensified.  
  • No specific information was provided to the public ahead of the vote on the tax implications of the proposed expenditure. 
  • This project appears to include significant funding for a controversial turf field and lighting under Parks & Recreation. But those funds are ineligible for reimbursement by the State. Why are ineligible turf field costs included in a “school appropriation”? Surreptitiously slipping those funds in now without explicit discussion denies the public the opportunity for debate around this highly controversial topic.   

Haste makes waste. That saying certainly applies to the rushed and chaotic Long Lots final approval process. Given the historic magnitude of this important project, the public deserved a more transparent and thoughtful deliberation.  Perhaps a citizen’s petition seeking a referendum will serve as a useful positive step towards ensuring more fiscal accountability.

Jennifer Johnson

RTM District 9 Representative