By Kerri Williams

WESTPORT – The chairman of the Long Lots Building Committee told members of two Representative Town Meeting committees Wednesday evening that the only time issue for the project to build a new $98-million elementary school involves a 14-day waiting period called for under the town’s charter.

What he didn’t tell them was that the state apparently changed the game for Westport suddenly on May 16.

The flurry of at least 10 town meetings in the next two weeks concerning the school project “has nothing to do with the state changing things,” Long Lots Building Committee Chairman Jay Keenan told RTM members at a joint meeting of the finance and education committees over a Zoom meeting.

However, both Finance Director Gary Conrad and Assistant Town Attorney Eileen Lavigne Flug told Westport Journal just the opposite earlier on Wednesday, saying that a “realignment” of state departments that control grant funding resulted in the town’s deadline for submitting requests to change. The new deadline of June 30 was some four months earlier than the original one of October, catching town officials off guard.

In addition, a town charter regulation requires a two-week break period to allow for the opportunity to file for a public referendum. That means that the RTM, which is the ultimate deciding town body on financial matters, must approve the project’s appropriation request by June 16 before it can be submitted to the state, Flug said.

If the town fails to meet the June 30 deadline, the grant funding would not be in the 2026-’27 state budget, and the opening of the new school, scheduled for 2027, would be delayed again unless the town made up for the gap in state funding.

Even as an RTM member, Keenan said he had not been aware of the charter provision that calls for a two-week waiting period on any appropriation over $500,000, which allows time for the public to request a referendum.

Contradictory information shared with RTM members

Seth Braunstein, chairman of the RTM’s finance committee, on Wednesday evening reiterated Keenan’s statement that the state changes were not an issue in the timing. “The only real difference is two weeks from what we originally anticipated,” he said.

Lauren Karpf, chair of the RTM’s education committee, addressed those at the meeting on the issue of timing, acknowledging that it “isn’t ideal.”  However, she reminded members that they have been getting periodic updates about the project and should be staying “up to speed.”

“If we met in a month, nothing would be drastically different,” she said.

During the meeting, Keenan presented architectural drawings and details of the $98 million project, adding that an updated cost estimate will be coming at the end of this week. He said the committee will be asking the state to reimburse about 20 percent of the total cost. Conrad told Westport Journal the requested reimbursement will be between 13 percent and 22 percent of the total cost.

When asked by Braunstein if the project cost could change, Keenan said that “nothing is guaranteed,” but that the committee has been getting independent estimates to be sure the figures are accurate.

“You never know until you go out to bid,” Keenan said. He added that “a lot of schools are being built right now,” which could factor into the cost, as well as the talk of tariffs that is constantly changing. “A lot of things play into this,” he said.

Kerri Williams is a freelance writer who has worked in journalism for years, including as a reporter for the Norwalk Hour and managing editor of the Norwalk Citizen-News.

Westport Journal Executive Editor John Palmer contributed to this report.