By Andy Brophy

WESTPORT-Town legislators on Monday night discussed how to proceed if the state Department of Transportation refuses to lower the proposed height of a replacement bridge for the William F. Cribari Memorial Bridge so tractor trailers can’t cross it.
The height of the proposed replacement bridge is 13 feet, 10 inches, while Representative Town Meeting members want it lowered to 12 feet, seven inches, which is the existing bridge’s effective height due to an electrical box on the bridge.
The RTM’s Transit Committee also discussed consequences of a long impasse between town residents and the DOT, which included the potential loss of federal funding on the estimated $78 million to $86 million project and further deterioration of the existing bridge.
If the existing bridge, built in 1884, deteriorates enough that replacing it becomes an emergency, the town would lose its voice on the project, said Valerie Seiling Jacobs, co-chairman of Save Westport Now.
If the DOT won’t lower the height of the proposed replacement bridge so tractor trailers can’t cross it, a chart presented by Melissa Levy, chairwoman of the Transit Committee, calls for the RTM to:
- Request a “design exception” so the replacement bridge’s clearance is 12 feet, seven inches.
- Request a traffic study to determine anticipated truck traffic flow from Interstate 95 and potential traffic flow if the Office of the State Traffic Administration approves “No Thru Truck” designations on Bridge Street, Greens Farms Road and Compo Road North.
- Ask the Board of Selectmen, which serves as Westport’s Local Traffic Authority, to evaluate and apply to the OSTA for “No Thru Truck” designations on all affected roads.
- Ask the Board of Selectmen to apply to OSTA for “no truck” restrictions on the Cribari Bridge or, alternatively, “no truck” restrictions during morning and afternoon rush hours.
- Ask town departments to evaluate and implement weight restrictions on roadways, speed bumps, additional stop signs and roadside sensors; manage navigation apps; and ask DOT to replace or repair traffic lights.
- Evaluate all potential ordinances to protect local roads, including Bridge Street, Greens Farms Road and Compo Road North.
- Evaluate tolls or congestion pricing on the replacement bridge, subject to state and federal approvals.
Levy said First Selectman Kevin Christie represented the town and that the town should ask for a “design exception” from the DOT on the replacement bridge’s height. “That, I think, is the number-one goal,” she said. Later, she said, “I don’t think we’re trying to eliminate all trucks – it’s the semi-tractor trailer trucks.”
Shannon Taylor of Bridge Street said, “If they can’t come now, we should be maintaining the status quo.”
The existing Cribari bridge is 13 feet, 10 inches tall, but an electrical box on the bridge lowers its clearance height to 12 feet, seven inches.
Town resident Bob Caporale said the state could remove the electrical box so clearance on the existing bridge is 13 feet, 10 inches. “The state can move that and will,” he said. “It’s an electrical box that the state will move.”
Werner Liepolt of Bridge Street said the electrical box already had been removed. “That electrical box is gone. It’s been removed,” he said, adding that people in Ninety 9 Bottles on Bridge Square “see trucks traversing the bridge all the time now.”
Peter Gold, RTM D-7, said a temporary bridge would exist for three years while a new Cribari Bridge is built. “We need to make sure whatever they design for the Cribari Bridge also applies to the temporary bridge,” he said.
Richard Lowenstein, RTM D-5, said residents should think about the potential loss of federal funding on the project, whether the bridge replacement would go forward without it, and whether they’d be happy if it didn’t.
Louis Mall, RTM D-2, asked, “Who will be responsible if we delay … and we don’t build a new bridge? Who’s going to be responsible if this bridge collapses?”
“We have a responsibility to public safety to build a safe bridge,” Mall said.
Ben Meyer, a former engineer, said photos of the existing bridge “are kind of scary.”
Levy said, “I do see the federal funding as a major issue and not something we should lose.”
But Jacobs said some residents are so angry about the possibility of tractor trailers crossing the bridge that they’re ready to sue. “If we come to that, it’s going to be a very sad day,” she said.
Wendy Batteau, RTM D-8, said Bridge Street met all six of the state’s criteria for a “No Thru Trucks” designation, but added an application for that designation has to be made by the Board of Selectmen and is a fairly long process.
Caporale said a “No Thru Trucks” designation on local roads would have to be done in tandem with lowering the height of the proposed bridge so truck drivers don’t travel up to the bridge and have to turn around.
Meanwhile, the DOT agreed to extend its comments on mitigation measures on its proposed replacement bridge to Dec. 11, Levy said. The previous deadline was Nov. 27.
Christie’s Cribari Bridge Advisory Committee will meet for the first time at noon Wednesday, Levy said. As of Monday night, notice of the meeting hadn’t been posted on the town’s website so its location was unclear.
Levy said she and Ward French, chairman of Christie’s committee, were “very much aligned on presenting a unified voice to state authorities.”
“I do think the message has been sent – we do not want trucks. That’s the one area where we are one voice,” she said.
Levy said the next RTM Transit Committee meeting likely would be Nov. 30.

Andy Brophy
Andy Brophy is an experienced Fairfield County journalist. Andy was a staff writer at The Connecticut Post for 10 years. He also wrote for the Norwalk Hour, Fairfield Minuteman, Fairfield Patch and weekly newspapers in Westport, Fairfield and Norwalk. When not reporting, Andy enjoys playing chess and listening to pianist Art Tatum. .